Free practice test · No signup
Free Red Seal Ironworker (Generalist) (420B) Practice Test
30 original questions with explanations. Pick an answer to check it instantly.
Question 1 · A – Occupational skills
On an Ontario construction project, above what fall height does O. Reg. 213/91 generally require a worker to be protected by a fall protection method such as guardrails or a fall arrest system?
Show answer without guessing
Answer: A. More than 3 m
Ontario's construction regulation requires fall protection where a worker could fall more than 3 m. Lower thresholds apply in special cases, for example a fall of more than 1.2 m from a wheelbarrow route or any fall into operating machinery, water or a hazardous substance.
Check it: O. Reg. 213/91 s. 26
Question 2 · A – Occupational skills
What is the purpose of a flashback arrestor on an oxy-fuel outfit?
Show answer without guessing
Answer: B. To stop a flame travelling back into the hose, regulator or cylinder
A flashback arrestor stops a flame front from moving back up the hose toward the regulator and cylinder. Check valves, a separate component, stop reverse gas flow; many arrestors combine both functions.
Check it: CSA W117.2
Question 3 · A – Occupational skills
What is the mass of a steel plate 2000 mm x 1000 mm x 25 mm? (Steel is about 7850 kg/m³.)
Show answer without guessing
Answer: D. About 393 kg
Volume = 2.0 m x 1.0 m x 0.025 m = 0.05 m³. Mass = 0.05 x 7850 = 392.5 kg, about 393 kg. Converting all dimensions to metres first avoids errors.
Check it: Formula: mass = volume x density
Question 4 · A – Occupational skills
What is the main reason for keeping a deck or floor free of loose rebar, scrap and bolts?
Show answer without guessing
Answer: B. To prevent slips and trips, and to stop material from falling to lower levels
Housekeeping prevents tripping hazards at height and stops loose material from falling or being kicked off the edge onto workers below.
Check it: NOA Block A – organizes work
Question 5 · B – Rigging and hoisting
A 4000 kg load is lifted with a two-leg bridle. Each leg makes a 60° angle with the horizontal. What is the approximate tension in each leg?
Show answer without guessing
Answer: B. About 2310 kg
Each leg carries half the load divided by the sine of the angle from horizontal: (4000 / 2) / sin 60° = 2000 / 0.866 = 2309 kg. The steeper the legs, the closer the tension gets to half the load.
Check it: Sling angle formula; CSA Z150 / ASME B30.9 sling angle factors
Question 6 · B – Rigging and hoisting
In a 6x19 class wire rope, what do the numbers mean?
Show answer without guessing
Answer: C. Six strands with about 19 wires per strand
The first number is the number of strands and the second is the (nominal) number of wires per strand. More, smaller wires (e.g. 6x36) give more flexibility; fewer, larger wires resist abrasion better.
Check it: Wire rope nomenclature
Question 7 · B – Rigging and hoisting
Which of these is a removal criterion for a synthetic web sling?
Show answer without guessing
Answer: C. Missing or illegible identification tag
Synthetic slings must be removed if the tag is missing or unreadable, and for cuts, holes, tears, broken stitching, burns, melting, chemical damage, embedded particles or exposed red warning yarns.
Check it: ASME B30.9 synthetic sling removal criteria
Question 8 · B – Rigging and hoisting
A line passes through a snatch block and turns 180°, with a line pull of 10 kN in each part. What load acts on the snatch block anchorage?
Show answer without guessing
Answer: A. About 20 kN
When the line turns 180°, both parts pull in the same direction, so the block and its anchor see twice the line pull. At 90° the load is about 1.41 times the line pull.
Check it: Snatch block load factors
Question 9 · B – Rigging and hoisting
In a tandem lift, why must the load share on each crane be calculated carefully?
Show answer without guessing
Answer: C. Movement or tilting of the load can shift weight onto one crane
If one crane hoists faster or the load tilts, the load shifts toward one crane. Plans calculate each crane's share at the worst position and allow a margin below chart capacity.
Check it: CSA Z150 (multiple crane lifts)
Question 10 · B – Rigging and hoisting
A steel pipe has an outside diameter of 300 mm, a wall thickness of 10 mm and a length of 6 m. What is its approximate mass?
Show answer without guessing
Answer: B. About 429 kg
Cross-section area = π/4 x (0.300² - 0.280²) = π/4 x 0.0116 = 0.00911 m². Volume = 0.00911 x 6 = 0.0547 m³. Mass = 0.0547 x 7850 = 429 kg.
Check it: Formula: volume of a hollow cylinder
Question 11 · C – Cranes
Which CSA standard covers safety for mobile cranes in Canada?
Show answer without guessing
Answer: D. CSA Z150
CSA Z150 is the safety code on mobile cranes. CSA Z248 covers tower cranes, CSA B167 overhead travelling cranes, hoists and monorails, and CSA W59 welded steel construction.
Check it: CSA Z150
Question 12 · C – Cranes
When erecting a tower crane, which document controls the assembly sequence and bolt torques?
Show answer without guessing
Answer: C. The manufacturer's erection manual and the engineered erection plan
Tower crane erection follows the manufacturer's instructions and an engineered plan for the site (foundation, ties, sequence, torques). CSA Z248 requires competent supervision and inspection.
Check it: CSA Z248
Question 13 · C – Cranes
Before disassembling a tower crane, what preparation is required?
Show answer without guessing
Answer: B. A disassembly plan, an adequate assist crane and suitable wind and site conditions
Dismantling reverses the erection sequence under a planned procedure, often with a mobile crane. The assist crane must reach the heaviest components at the required radius, and wind limits apply.
Check it: CSA Z248
Question 14 · D – Reinforcing
In Canadian metric rebar sizes, what is the nominal mass of a 15M bar per metre?
Show answer without guessing
Answer: C. 1.570 kg/m
CSA G30.18 lists 15M as 16.0 mm nominal diameter, 200 mm² area and 1.570 kg/m. 10M is 0.785 kg/m, 20M 2.355 kg/m and 25M 3.925 kg/m.
Check it: CSA G30.18 (bar sizes)
Question 15 · D – Reinforcing
Which type of bar support is commonly used on soil or a vapour barrier for slabs on grade?
Show answer without guessing
Answer: A. Precast concrete blocks (dobies) or supports with sand plates
On soil, wire chairs sink in. Precast concrete blocks or chairs with plates spread the load and maintain cover. Wood is not left in concrete because it rots and wicks moisture.
Check it: RSIC Manual (bar supports)
Question 16 · D – Reinforcing
A wall is 12 m long. Vertical 15M bars are placed at 400 mm O.C., starting and ending 200 mm from the ends. How many bars are needed in one face?
Show answer without guessing
Answer: D. 30
Distance between end bars = 12,000 - 400 = 11,600 mm. Spaces = 11,600 / 400 = 29. Bars = 29 + 1 = 30.
Check it: Bar spacing calculation
Question 17 · D – Reinforcing
Why must bar spacing allow enough clear space between bars?
Show answer without guessing
Answer: D. So concrete and aggregate can flow between bars and fully surround them
Minimum clear spacing (related to bar size and aggregate size) lets concrete consolidate around bars. Congested reinforcement can cause honeycombing and voids.
Check it: CSA A23.1 (spacing)
Question 18 · D – Reinforcing
How should rebar be stored on site?
Show answer without guessing
Answer: C. Off the ground on dunnage, sorted by mark, and protected as required
Storing bars on dunnage keeps them clean and accessible. Sorting by mark speeds placing. Coated bars may need covering from UV.
Check it: RSIC handling and storage
Question 19 · E – Pre-stresses/post-tensions
What is the main difference between pre-tensioning and post-tensioning?
Show answer without guessing
Answer: A. Pre-tensioning stresses strands before casting; post-tensioning stresses tendons afterward
In pre-tensioning (usually in a precast plant) strands are tensioned between abutments, concrete is cast, and the strands are released once it reaches strength. In post-tensioning, tendons in sheathing or ducts are stressed after the concrete has gained the required strength.
Check it: NOA Block E – places pre-stressed/post-tensioning systems
Question 20 · E – Pre-stresses/post-tensions
Why must stressing jacks and gauges be calibrated?
Show answer without guessing
Answer: B. So the gauge pressure accurately represents the force in the tendon
Jacks and gauges are calibrated as a pair; the calibration chart converts gauge pressure to force. Uncalibrated equipment can overstress or understress tendons.
Check it: PTI stressing practice
Question 21 · F – Erection, assembly and installation
Which CSA standard governs the design, fabrication and erection of structural steel buildings in Canada?
Show answer without guessing
Answer: D. CSA S16
CSA S16 (Design of steel structures) includes requirements for fabrication and erection of structural steel, including bolting, tolerances and temporary bracing. Welding follows CSA W59.
Check it: CSA S16
Question 22 · F – Erection, assembly and installation
Can pretensioned A490 (F3125 Grade A490) bolts be reused?
Show answer without guessing
Answer: C. No, they must not be reused or retightened after full pretensioning
Pretensioning stretches high-strength bolts. A490 bolts and galvanized A325 bolts must not be reused. Black A325 bolts may be reused only if approved.
Check it: CSA S16; RCSC specification
Question 23 · F – Erection, assembly and installation
What is cross-laminated timber (CLT)?
Show answer without guessing
Answer: A. Panels of lumber layers glued at right angles, used as walls and floors
CLT is an engineered wood panel of crosswise layers. Ironworkers on mass timber projects install panels and steel connections, using the manufacturer's lifting systems.
Check it: Mass timber construction
Question 24 · F – Erection, assembly and installation
When installing a column splice, what is usually done first?
Show answer without guessing
Answer: D. Bolt the splice plates to hold alignment, then plumb and finish
Splice plates are bolted to hold the upper column in alignment. After plumbing, splices are fully bolted or welded as detailed.
Check it: Erection practice
Question 25 · F – Erection, assembly and installation
What is the main purpose of an erection sequence drawing?
Show answer without guessing
Answer: A. To show the order in which members are erected for stability
Erection sequence drawings show the order and stages, making sure each stage is stable before the next.
Check it: Erection planning
Question 26 · F – Erection, assembly and installation
What is a curtain wall?
Show answer without guessing
Answer: A. A non-load-bearing exterior wall hung from the structure
Curtain walls carry their own weight and wind loads to the structure through anchors but do not support floors. Ironworkers often install them.
Check it: Building terminology
Question 27 · F – Erection, assembly and installation
What is the purpose of anchor bolt sleeves in machine foundations?
Show answer without guessing
Answer: D. To allow slight adjustment of the anchor bolt position
Sleeves around anchor bolts let the bolt move slightly to align with the machine's holes before grouting.
Check it: Machinery installation practice
Question 28 · F – Erection, assembly and installation
Why is a minimum edge distance required for bolt holes in steel members?
Show answer without guessing
Answer: B. Holes too close to an edge can tear out under load
CSA S16 sets minimum edge distances so the steel between the hole and the edge can carry bearing forces without tearing. Field holes must respect these distances.
Check it: CSA S16 (edge distance)
Question 29 · G – Maintenance and upgrading
Before dismantling part of an existing steel structure, what is the most important planning step?
Show answer without guessing
Answer: B. Determine how removal will affect stability and follow an engineered removal sequence
Removing members changes load paths. A demolition or removal plan (often engineered) sets the sequence, shoring and rigging so remaining members stay stable.
Check it: NOA Block G – dismantles and removes components; O. Reg. 213/91 (demolition)
Question 30 · G – Maintenance and upgrading
When removing a large piece of equipment from a plant, what is necessary?
Show answer without guessing
Answer: A. Isolating and decommissioning it before rigging and removal
Equipment is decommissioned: utilities and energy isolated, fluids drained and connections removed before rigging.
Check it: NOA Block G – dismantles and removes components
These are VoltExam questions written for the Red Seal Ironworker (Generalist) Interprovincial Exam, not official exam questions. Each shows the rule or standard to check it against. New to this exam? Read the Red Seal Ironworker (Generalist) (420B) guide.
Last checked against Red Seal Program (with provincial and territorial apprenticeship authorities) on .
Want the other 570 questions?
- ✓ 600 Red Seal Ironworker (Generalist) practice questions, every answer explained and cited
- ✓ Full-length timed mock exams: 120 questions, 4 hours, scored against 70%
- ✓ Practise by topic and review every question you missed
- ✓ Every other Canadian exam on VoltExam included
Official sources
- Red Seal – Ironworker (Generalist) trade page ↗
- Red Seal – Ironworker (Generalist) exam breakdown ↗
- Red Seal – Ironworker (Generalist) RSOS examination weightings ↗
- Red Seal – Red Seal Occupational Standard: Ironworker (Generalist) ↗
- Red Seal – Overview of the Red Seal Examination ↗
- Skilled Trades Ontario – Ironworker – Generalist ↗
- Skilled Trades Ontario – Trades information (420A and 420B) ↗
- Skilled Trades Ontario – Ironworker – Generalist (420B) apprenticeship training standard (PDF) ↗
Sources checked November 3, 2026. VoltExam is independent and not affiliated with Red Seal Program (with provincial and territorial apprenticeship authorities). Rules change: confirm details with the official source before your exam.