Short answer

Add the four cycle segments to get the cycle time, divide the working minutes in the hour by it for trips per hour, then multiply by the payload. A 15.5 minute cycle and 36 t payload in a 50 minute hour gives about 116 t/h.

Cycle time
15.5 min
Trips per hour
3.23
Production
116 t/h

Studying for the Red Seal Heavy Duty Equipment Technician (421A) exam?

Calculations like this are on the exam. Test yourself with 30 free questions, or try all 618 free for 3 days.

Free trial for new members on the Monthly plan, then C$8.99/month until you cancel.

Formula

Cycle = Load + Haul + Dump + Return · Trips/h = Minutes ÷ Cycle · t/h = Trips/h × Payload

Worked example

Cycle = 3.0 + 6.5 + 1.0 + 5.0 = 15.5 min. Trips = 50 ÷ 15.5 = 3.23. Production = 3.23 × 36 = 116 t/h.

Before you rely on it

  • Working minutes per hour account for breaks, waits and delays. Exams usually give you the figure.
  • Production is limited by whichever of loading or hauling is the bottleneck.
  • Use the truck's rated payload, not its body capacity.