Free calculator · Heavy Duty Equipment Technician
Haul Truck Production Calculator
Short answer
Add the four cycle segments to get the cycle time, divide the working minutes in the hour by it for trips per hour, then multiply by the payload. A 15.5 minute cycle and 36 t payload in a 50 minute hour gives about 116 t/h.
- Cycle time
- 15.5 min
- Trips per hour
- 3.23
- Production
- 116 t/h
Studying for the Red Seal Heavy Duty Equipment Technician (421A) exam?
Calculations like this are on the exam. Test yourself with 30 free questions, or try all 618 free for 3 days.
Free trial for new members on the Monthly plan, then C$8.99/month until you cancel.
Formula
Cycle = Load + Haul + Dump + Return · Trips/h = Minutes ÷ Cycle · t/h = Trips/h × Payload
Worked example
Cycle = 3.0 + 6.5 + 1.0 + 5.0 = 15.5 min. Trips = 50 ÷ 15.5 = 3.23. Production = 3.23 × 36 = 116 t/h.
Before you rely on it
- Working minutes per hour account for breaks, waits and delays. Exams usually give you the figure.
- Production is limited by whichever of loading or hauling is the bottleneck.
- Use the truck's rated payload, not its body capacity.