Wheel Loader Production Calculator

Short answer

Bucket payload is the heaped capacity times the fill factor. Passes per hour is working minutes times 60 divided by the cycle time. A 4.5 m³ bucket at 90% fill and a 40 s cycle, working 50 minutes an hour, moves 304 m³ per hour and needs 5 passes to fill a 20 m³ truck.

Payload per pass
4.05 m³
Passes per hour
75
Production
304 m³/h
Passes to fill the truck
5

Studying for the Red Seal Heavy Duty Equipment Technician (421A) exam?

Calculations like this are on the exam. Test yourself with 30 free questions, or try all 618 free for 3 days.

Free trial for new members on the Monthly plan, then C$8.99/month until you cancel.

Formula

Payload = Bucket × Fill% · Passes/h = Minutes × 60 ÷ Cycle (s) · m³/h = Passes/h × Payload

Worked example

Payload = 4.5 × 0.90 = 4.05 m³. Passes = 50 × 60 ÷ 40 = 75. Production = 75 × 4.05 = 304 m³/h. Truck passes = ⌈20 ÷ 4.05⌉ = 5.

Before you rely on it

  • Heaped capacity is a rating, not what the bucket carries in the pile. The fill factor corrects for that.
  • Passes to fill a truck are whole buckets, so always round up.
  • Site conditions and the manufacturer's data decide real production.