  1. Question 1 · E – Pre-stresses/post-tensions

    What is the main difference between pre-tensioning and post-tensioning?

    Show answer without guessing

    Answer: A. Pre-tensioning stresses strands before casting; post-tensioning stresses tendons afterward

    In pre-tensioning (usually in a precast plant) strands are tensioned between abutments, concrete is cast, and the strands are released once it reaches strength. In post-tensioning, tendons in sheathing or ducts are stressed after the concrete has gained the required strength.

    Check it: NOA Block E – places pre-stressed/post-tensioning systems

  2. Question 2 · E – Pre-stresses/post-tensions

    Why must stressing jacks and gauges be calibrated?

    Show answer without guessing

    Answer: B. So the gauge pressure accurately represents the force in the tendon

    Jacks and gauges are calibrated as a pair; the calibration chart converts gauge pressure to force. Uncalibrated equipment can overstress or understress tendons.

    Check it: PTI stressing practice

  3. Question 3 · E – Pre-stresses/post-tensions

    What is an unbonded monostrand tendon?

    Show answer without guessing

    Answer: A. A single greased strand encased in plastic sheathing

    Unbonded monostrand tendons are greased and sheathed so the strand can move inside during stressing and remains unbonded for its life. They are common in building slabs.

    Check it: NOA Block E; PTI unbonded tendon practice

  4. Question 4 · E – Pre-stresses/post-tensions

    Before stressing post-tensioned slabs, what concrete condition must be met?

    Show answer without guessing

    Answer: A. The concrete must reach the minimum strength specified by the engineer

    Stressing puts high bearing stress behind anchors. Concrete must reach the specified strength (verified by field-cured cylinders or other approved methods) to avoid anchor blowouts.

    Check it: Project specifications; PTI

  5. Question 5 · E – Pre-stresses/post-tensions

    In encapsulated unbonded systems, why are the anchors fitted with sleeves and end caps?

    Show answer without guessing

    Answer: A. To fully seal the strand and anchor from moisture and chlorides

    Encapsulated systems provide a watertight seal from anchor to anchor, which is required in aggressive environments such as parking structures.

    Check it: PTI encapsulated systems

  6. Question 6 · E – Pre-stresses/post-tensions

    What is the purpose of a 'stressing record'?

    Show answer without guessing

    Answer: D. To document jack, gauge, pressures and elongations for each tendon

    Stressing records list the tendon ID, jack and gauge numbers, pressures and measured elongations. The engineer reviews them before tails are cut.

    Check it: Project specifications; PTI

  7. Question 7 · E – Pre-stresses/post-tensions

    In a precast plant, what is 'detensioning' or release?

    Show answer without guessing

    Answer: B. Transferring strand force into the cured concrete by releasing the strands

    When concrete reaches release strength, the strands are cut or released gradually, transferring the prestress to the member. The sequence is set to avoid cracking.

    Check it: Precast plant practice

  8. Question 8 · E – Pre-stresses/post-tensions

    When placing tendons in a slab with mild reinforcing, which usually takes priority for position?

    Show answer without guessing

    Answer: C. Tendon profiles, with mild steel adjusted around them as detailed

    Tendon profiles are critical, so rebar is typically placed to suit the tendon heights. Coordination drawings show the sequence and any conflicts are referred to the engineer.

    Check it: Project specifications; PTI

These are VoltExam questions written for the Red Seal Ironworker (Generalist) Interprovincial Exam, not official exam questions. Take the full free practice test or read the Red Seal Ironworker (Generalist) (420B) guide.

Last checked against Red Seal Program (with provincial and territorial apprenticeship authorities) on .

Practise Red Seal Ironworker (Generalist) (420B) by topic

Want every Red Seal Ironworker (Generalist) (420B) topic and the timed mock exams?

  • ✓ 600 Red Seal Ironworker (Generalist) practice questions, every answer explained and cited
  • ✓ Full-length timed mock exams: 120 questions, 4 hours, scored against 70%
  • ✓ Practise by topic and review every question you missed
  • ✓ Every other Canadian exam on VoltExam included

From

C$8.99/month

3-day free trial · or C$44.99 once for lifetime

Try all 600 free for 3 days

Free trial for new members on the Monthly plan, then C$8.99/month until you cancel. See all plans