Red Seal Mobile Crane Operator (339A): E – Plans lift, prepares site and sets up crane practice questions
10 original questions on this part of the exam, each with an explanation and a reference you can check.
What this area covers (16 questions on the exam)
Pre-lift planning (9) and setting up the crane (7): lift plans, power lines, wind, ground bearing, outrigger setup and levelling.
Question 1 · E – Plans lift, prepares site and sets up crane
A crane must be set up beside overhead power lines. As a general rule, how should the lines be treated until the owner confirms otherwise?
Show answer without guessing
Answer: B. As energized, even if the lines look insulated
Power lines must be assumed to be live until the utility owner confirms they are de-energized and grounded. Insulation on the wire, silence, missing signs or a spotter do not make a line safe, and contact can happen through the load or rigging as well.
Check it: O. Reg. 213/91 (Construction Projects)
Question 2 · E – Plans lift, prepares site and sets up crane
An outrigger reaction is 180 kN, carried on a square mat measuring 1.2 m x 1.2 m. What is the average ground bearing pressure under the mat?
Show answer without guessing
Answer: C. 125 kPa
Pressure = force / area. Mat area = 1.2 x 1.2 = 1.44 m². 180 kN / 1.44 m² = 125 kPa. Dividing by one side only gives 150 kPa, multiplying by the area gives 216 kPa, and a decimal slip gives 12.5 kPa.
Check it: Red Seal Occupational Standard: Mobile Crane Operator – Task 12
Question 3 · E – Plans lift, prepares site and sets up crane
As a general rule, what limits lifting a large, flat panel in wind?
Show answer without guessing
Answer: C. The manufacturer's wind limits, adjusted for the load's size and sail area
Wind pushes on the load's surface area, not just its weight, so a light but large panel can be uncontrollable. The operator manual and load chart give the maximum wind speed and how to reduce it for large sail area.
Check it: Crane manufacturer's load chart and operator manual (values given in the question)
Question 4 · E – Plans lift, prepares site and sets up crane
A crane will work in January on ground that is frozen at the surface, and daytime temperatures are expected to rise above 0°C. What is the best practice?
Show answer without guessing
Answer: C. Size mats for the unfrozen soil below, since frost can soften as it thaws
Frost can give a false sense of strength: when the surface thaws, bearing capacity can drop suddenly. Planning outrigger mats for the unfrozen soil bearing keeps the crane stable if the ground softens during the day.
Check it: Red Seal Occupational Standard: Mobile Crane Operator – Task 12
Question 5 · E – Plans lift, prepares site and sets up crane
A planned lift has a 11,800 kg load, 450 kg of rigging and a 900 kg hook block. The load chart rating at the working radius is 17,500 kg. What percentage of chart capacity is used?
Show answer without guessing
Answer: C. 75%
The crane must carry everything below the boom tip: 11,800 + 450 + 900 = 13,150 kg. 13,150 / 17,500 = 0.75, or about 75% of capacity. Using the load alone gives 67%, which understates the duty.
Check it: Crane manufacturer's load chart and operator manual (values given in the question)
Question 6 · E – Plans lift, prepares site and sets up crane
Unless the utility owner confirms otherwise, how must an overhead power line be treated?
Show answer without guessing
Answer: D. As energized, whether or not it looks insulated
Overhead lines are always assumed to be live until the owner confirms they are de-energized and grounded. Appearance and sound are not reliable indicators.
Check it: O. Reg. 213/91 (Construction Projects)
Question 7 · E – Plans lift, prepares site and sets up crane
Which describes a sound planning requirement for a tandem lift?
Show answer without guessing
Answer: B. A written plan setting each crane's share, the path, and signals
Load share depends on the centre of gravity and rigging, so it must be worked out in advance and written down. All participants must know their duties before hoisting starts.
Check it: Red Seal Occupational Standard: Mobile Crane Operator – Task 11
Question 8 · E – Plans lift, prepares site and sets up crane
Why is a test lift made just clear of the ground before the main hoist?
Show answer without guessing
Answer: C. To check the brakes, stability, rigging and balance of the load before lifting higher
Lifting a short distance and holding shows any slipping brakes, unbalanced loads or rigging problems while the load can still be set down safely.
Check it: Red Seal Occupational Standard: Mobile Crane Operator – Task 11
Question 9 · E – Plans lift, prepares site and sets up crane
A geotechnical report gives an allowable bearing pressure of 150 kPa. About how much mass can each square metre of this soil support?
Show answer without guessing
Answer: B. 15.3 t
150 kPa is 150 kN/m2. Dividing by 9.81 m/s2 converts force to mass: 150,000 / 9.81 = 15,291 kg, or 15.3 t per m2. Reading kPa directly as tonnes per m2 gives 150, which overstates it.
Check it: Crane manufacturer's load chart and operator manual (values given in the question)
Question 10 · E – Plans lift, prepares site and sets up crane
What should be done before setting up on a site where buried services may exist?
Show answer without guessing
Answer: A. Obtain utility locates, such as through Ontario One Call, and review the markings
Locates identify gas, electrical, water and other lines before the crane loads the ground. Memory and guesses are not reliable.
Check it: O. Reg. 213/91 (Construction Projects)
These are VoltExam questions written for the Red Seal Mobile Crane Operator Interprovincial Exam, not official exam questions. Take the full free practice test or read the Red Seal Mobile Crane Operator (339A) guide.
Free calculators for this exam: Sling Angle and Leg Tension Calculator, Crane Mat Ground Bearing Pressure Calculator.
Last checked against Red Seal Program (with provincial and territorial apprenticeship authorities) on .
Practise Red Seal Mobile Crane Operator (339A) by topic
Want every Red Seal Mobile Crane Operator (339A) topic and the timed mock exams?
- ✓ 600 Red Seal Mobile Crane Operator practice questions, every answer explained and cited
- ✓ Full-length timed mock exams: 110 questions, 4 hours, scored against 70%
- ✓ Practise by topic and review every question you missed
- ✓ Every other Canadian exam on VoltExam included
From
C$8.99/month
3-day free trial · or C$44.99 once for lifetime
Try all 600 free for 3 daysFree trial for new members on the Monthly plan, then C$8.99/month until you cancel. See all plans
Official sources
- Red Seal – Mobile Crane Operator trade page ↗
- Red Seal – Mobile Crane Operator exam breakdown ↗
- Red Seal – Mobile Crane Operator examination weightings ↗
- Red Seal – Mobile Crane Operator exam self-assessment guide (PDF) ↗
- Saskatchewan Apprenticeship – Mobile Crane Operator interprovincial exam information (PDF) ↗
- Skilled Trades Ontario – Hoisting Engineer – Mobile Crane Operator 1 ↗
- Skilled Trades Ontario – Trades information (339A, 339B, 339C) ↗