What this area covers (18 questions on the exam)

Planning the installation of HVAC/R systems (11), including loads and equipment selection, and planning the installation of control systems (7).

Answered 0 / 10Score 0
  1. Question 1 · C – Plans installation

    When planning the suction line for a split system where the evaporator is below the condensing unit, what is commonly installed at the base of a vertical suction riser?

    Show answer without guessing

    Answer: A. An oil trap (P-trap) so oil collects and is carried up the riser by refrigerant vapour

    Oil returns to the compressor by being swept along by vapour. At the base of a vertical suction riser, a short trap lets oil accumulate until vapour velocity carries it up. Line sizing must also keep riser velocity high enough for oil return.

    Check it: RSOS task C-7 (plans installation of HVAC/R systems)

  2. Question 2 · C – Plans installation

    A walk-in cooler is designed to hold product with high relative humidity, such as fresh vegetables. How does this affect the evaporator selection?

    Show answer without guessing

    Answer: B. Choose a coil with a small design TD between box air and refrigerant, to reduce moisture removal

    The colder the coil compared with the box air, the more moisture condenses on it and the drier the box becomes. A lower TD, which requires a larger coil, keeps relative humidity high and reduces product dehydration.

    Check it: RSOS task C-7 (load and equipment selection)

  3. Question 3 · C – Plans installation

    A product load calculation needs the heat removed to cool 500 kg of product from 20°C to 4°C. The product's specific heat above freezing is 3.6 kJ/kg·°C. How much heat must be removed?

    Show answer without guessing

    Answer: C. 28,800 kJ

    Sensible heat Q = m × c × ΔT = 500 kg × 3.6 kJ/kg·°C × (20 − 4)°C = 500 × 3.6 × 16 = 28,800 kJ. Using 20°C alone as the temperature change gives 36,000 kJ, which overstates the load.

    Check it: RSOS task C-7 (load calculation)

  4. Question 4 · C – Plans installation

    When planning a control system for a refrigeration unit, why is a 24 V AC control circuit commonly used for thermostats and relays?

    Show answer without guessing

    Answer: C. Low voltage cuts shock and fire risk in field wiring and allows smaller, cheaper thermostat wire and controls

    A Class 2 transformer supplies limited-energy 24 V power, so thermostat wiring can be smaller and is safer to handle. The low-voltage circuit then energizes contactor and relay coils that switch the line-voltage loads.

    Check it: RSOS task C-8 (plans installation of control systems)

  5. Question 5 · C – Plans installation

    Air flows across a coil at 800 L/s with a dry-bulb temperature drop of 11°C. Using sensible heat (W) = 1.2 × L/s × ΔT, what is the sensible capacity?

    Show answer without guessing

    Answer: C. About 10.6 kW

    Q = 1.2 × 800 × 11 = 10,560 W ≈ 10.6 kW. The 1.2 factor combines air density (about 1.2 kg/m³) and specific heat (about 1.0 kJ/kg·°C); leaving it out understates the load.

    Check it: RSOS task C-7 (load calculation)

  6. Question 6 · C – Plans installation

    200 kg of product is to be frozen from 10°C to −18°C. It freezes at −2°C. Specific heat above freezing is 3.5 kJ/kg·°C, below freezing 1.8 kJ/kg·°C, and latent heat of fusion is 240 kJ/kg. What is the total heat removed?

    Show answer without guessing

    Answer: D. 62,160 kJ

    Three steps: cool to freezing 200×3.5×12 = 8,400 kJ; freeze 200×240 = 48,000 kJ; cool below freezing 200×1.8×16 = 5,760 kJ. Total 62,160 kJ. Missing the latent step badly understates the load.

    Check it: RSOS task C-7 (load calculation)

  7. Question 7 · C – Plans installation

    For a walk-in cooler, which of these is usually the largest heat load component during product pull-down?

    Show answer without guessing

    Answer: D. Product load, the heat removed from warm product brought into the box

    When large amounts of warm product are loaded, removing their sensible heat dominates. Wall transmission, infiltration, people, lights and fan motors are added, but product load often controls the coil size.

    Check it: RSOS task C-7 (load calculation)

  8. Question 8 · C – Plans installation

    When planning refrigerant piping for a system with a large vertical suction riser and widely varying loads, what may be needed?

    Show answer without guessing

    Answer: D. A double suction riser so velocity stays high enough to return oil at minimum load

    A single riser sized for full load may be too large for adequate velocity at low load. With a double riser, the small riser carries oil at low load and both risers operate at full load.

    Check it: RSOS task C-7 (plans installation of HVAC/R systems)

  9. Question 9 · C – Plans installation

    Why would a ductless mini-split heat pump be selected for a home without existing ductwork?

    Show answer without guessing

    Answer: C. It heats and cools without ductwork, using a small line set between indoor and outdoor units

    Ductless systems connect indoor heads to an outdoor unit with refrigerant lines and control wiring through a small wall opening, avoiding major renovation for ducts.

    Check it: RSOS task C-7 (plans installation of HVAC/R systems)

  10. Question 10 · C – Plans installation

    Why is a 4–20 mA signal often chosen over 0–10 V for sensors with long wire runs?

    Show answer without guessing

    Answer: A. Current signals resist voltage drop and electrical noise, and 0 mA indicates a broken wire

    A current loop delivers the same current at the receiver regardless of wire resistance. The live zero at 4 mA lets the controller detect an open circuit.

    Check it: RSOS task C-8 (plans installation of control systems)

These are VoltExam questions written for the Red Seal Refrigeration and Air Conditioning Mechanic Interprovincial Exam, not official exam questions. Take the full free practice test or read the Red Seal Refrigeration Mechanic (313A) guide.

Last checked against Red Seal Program (with provincial and territorial apprenticeship authorities) on .

Practise Red Seal Refrigeration Mechanic (313A) by topic

Want every Red Seal Refrigeration Mechanic (313A) topic and the timed mock exams?

  • ✓ 600 Red Seal Refrigeration Mechanic practice questions, every answer explained and cited
  • ✓ Full-length timed mock exams: 125 questions, 4 hours, scored against 70%
  • ✓ Practise by topic and review every question you missed
  • ✓ Every other Canadian exam on VoltExam included

From

C$8.99/month

3-day free trial · or C$44.99 once for lifetime

Try all 600 free for 3 days

Free trial for new members on the Monthly plan, then C$8.99/month until you cancel. See all plans