Practice by topic · No signup
Red Seal Refrigeration Mechanic (313A): E – Performs commissioning practice questions
11 original questions on this part of the exam, each with an explanation and a reference you can check.
What this area covers (21 questions on the exam)
Commissioning HVAC/R systems (13), including pressure testing, evacuation, charging and start-up checks, and commissioning control systems (8).
Question 1 · E – Performs commissioning
During commissioning, a three-phase scroll compressor is noisy and the suction and discharge pressures barely change after start-up. What is the most likely cause?
Show answer without guessing
Answer: B. The compressor is running backward because the phase rotation is reversed
A scroll compressor only pumps in one direction. With two supply phases reversed it runs backward, makes abnormal noise and builds no pressure difference. Shut it down quickly and swap two line leads, then confirm normal pressures.
Check it: RSOS task E-11 (commissions HVAC/R systems)
Question 2 · E – Performs commissioning
A three-phase supply measures 208 V, 212 V and 204 V between phases. What is the voltage imbalance?
Show answer without guessing
Answer: B. About 1.9%
Average = (208 + 212 + 204) ÷ 3 = 208 V. The largest deviation from average is 4 V. Imbalance = 4 ÷ 208 × 100 ≈ 1.9%. Even small voltage imbalance causes much larger current imbalance and motor heating.
Check it: RSOS task E-11 (commissioning – electrical checks)
Question 3 · E – Performs commissioning
When commissioning a new system, why is a standing vacuum (decay) test performed after reaching the target vacuum?
Show answer without guessing
Answer: D. A steady rise that levels off indicates moisture still boiling off, while a continuous rise to atmosphere indicates a leak
After isolating the pump, watch the micron gauge. If pressure rises and then stabilizes, moisture is still evaporating and more evacuation is needed. If it keeps rising steadily, air is leaking in and the leak must be found and fixed.
Check it: RSOS task E-11 (commissioning – evacuation)
Question 4 · E – Performs commissioning
While commissioning a low-pressure control for a pumpdown system, you set it to cut out at 70 kPa and cut in at 170 kPa (gauge). What is the differential?
Show answer without guessing
Answer: B. 100 kPa
Differential is the difference between the cut-in and cut-out settings: 170 − 70 = 100 kPa. Too small a differential causes short cycling; too large allows the box temperature to drift.
Check it: RSOS task E-12 (commissions control systems)
Question 5 · E – Performs commissioning
When commissioning a heat pump, what must be verified about the reversing valve?
Show answer without guessing
Answer: A. That it shifts properly between heating and cooling, with its solenoid energized in the mode the manufacturer specifies
Manufacturers differ: some energize the reversing valve in cooling, others in heating. Confirm the thermostat setup matches the equipment, then check that the valve shifts and refrigerant temperatures change correctly in each mode.
Check it: RSOS task E-12 (commissions control systems)
Question 6 · E – Performs commissioning
Air flows across a coil at 1,200 L/s with a dry-bulb temperature drop of 10°C. Using sensible heat (W) = 1.2 × L/s × ΔT, what is the sensible capacity?
Show answer without guessing
Answer: C. About 14.4 kW
Q = 1.2 × 1,200 × 10 = 14,400 W ≈ 14.4 kW. The 1.2 factor combines air density (about 1.2 kg/m³) and specific heat (about 1.0 kJ/kg·°C); leaving it out understates the load.
Check it: RSOS task E-11 (commissioning – capacity checks)
Question 7 · E – Performs commissioning
An automatic-reset high-pressure control on a condensing unit is set to cut out at 2,900 kPa (gauge) with a 600 kPa differential. At what pressure will it reset and allow the compressor to restart?
Show answer without guessing
Answer: B. 2,300 kPa
A high-pressure control opens on rising pressure and closes again when pressure falls by the differential: 2,900 − 600 = 2,300 kPa. A low-pressure control works the opposite way, cutting in above its cut-out.
Check it: RSOS task E-12 (commissions control systems)
Question 8 · E – Performs commissioning
What is the purpose of measuring the compressor amperage during commissioning?
Show answer without guessing
Answer: B. To confirm it runs within its nameplate rating and detect electrical or mechanical problems
Current compared with RLA indicates load. High current suggests high head pressure, overcharge or voltage problems; low current can indicate an undercharge or internal problems.
Check it: RSOS task E-11 (commissions HVAC/R systems)
Question 9 · E – Performs commissioning
When starting a water-cooled system, which water-side measurements should be taken?
Show answer without guessing
Answer: B. Entering and leaving water temperatures and flow or pressure drop across the exchanger
Water temperatures and flow confirm the condenser or evaporator is getting design flow and transferring heat.
Check it: RSOS task E-11 (commissions HVAC/R systems)
Question 10 · E – Performs commissioning
During commissioning, a defrost timer is set for four defrosts a day with a 40-minute fail-safe. The coil is still frosted after defrost terminates on temperature. What should you check?
Show answer without guessing
Answer: B. The location and setting of the termination sensor, and whether all heaters are working
If defrost ends while frost remains, the termination sensor may be mounted in a warm area or set too low, or a heater may have failed.
Check it: RSOS task E-12 (commissions control systems)
Question 11 · E – Performs commissioning
During commissioning of a low-pressure control used for temperature control on a small cooler, the box holds 1°C too warm on average. What adjustment is appropriate?
Show answer without guessing
Answer: B. Lower the cut-in and cut-out pressures slightly so the evaporator runs colder before stopping
Lowering the pressure settings lowers the corresponding saturation temperatures, so the coil and box run colder. Make small changes and observe over several cycles.
Check it: RSOS task E-12 (commissions control systems)
These are VoltExam questions written for the Red Seal Refrigeration and Air Conditioning Mechanic Interprovincial Exam, not official exam questions. Take the full free practice test or read the Red Seal Refrigeration Mechanic (313A) guide.
Last checked against Red Seal Program (with provincial and territorial apprenticeship authorities) on .
Practise Red Seal Refrigeration Mechanic (313A) by topic
Want every Red Seal Refrigeration Mechanic (313A) topic and the timed mock exams?
- ✓ 600 Red Seal Refrigeration Mechanic practice questions, every answer explained and cited
- ✓ Full-length timed mock exams: 125 questions, 4 hours, scored against 70%
- ✓ Practise by topic and review every question you missed
- ✓ Every other Canadian exam on VoltExam included
From
C$8.99/month
3-day free trial · or C$44.99 once for lifetime
Try all 600 free for 3 daysFree trial for new members on the Monthly plan, then C$8.99/month until you cancel. See all plans
Official sources
- Red Seal – Refrigeration and Air Conditioning Mechanic trade page ↗
- Red Seal – Refrigeration and Air Conditioning Mechanic exam information (breakdown) ↗
- Red Seal – Exam Preparation Guide ↗
- Skilled Trades Ontario – Refrigeration and Air Conditioning Systems Mechanic ↗
- Skilled Trades Ontario – Refrigeration and Air Conditioning Systems Mechanic (313A) 2025 trade report ↗
- Ontario – Certificate to handle refrigerants (ODP card) ↗
Sources checked November 14, 2026. VoltExam is independent and not affiliated with Red Seal Program (with provincial and territorial apprenticeship authorities). Rules change: confirm details with the official source before your exam.