Red Seal Refrigeration Mechanic (313A): D – Performs installation practice questions
12 original questions on this part of the exam, each with an explanation and a reference you can check.
What this area covers (26 questions on the exam)
Installing HVAC/R systems (16), such as compressors, condensers, evaporators, metering devices and piping, and installing control systems (10).
Question 1 · D – Performs installation
Which method is correct for adding a zeotropic blend such as R-407C to a system?
Show answer without guessing
Answer: A. Remove it from the cylinder as liquid and meter it into the system so it does not slug the compressor
The components of a zeotropic blend boil at different temperatures, so drawing vapour off the top changes the mixture left in the cylinder and the composition charged. Taking liquid keeps the blend at its design ratio; meter it slowly into the suction side or charge into the liquid line with the system off.
Check it: RSOS task D-9 (installs HVAC/R systems – charging)
Question 2 · D – Performs installation
When installing a thermostatic expansion valve, where is the sensing bulb normally attached?
Show answer without guessing
Answer: C. On the suction line near the evaporator outlet, in good contact and insulated from ambient air
The TXV regulates refrigerant flow to hold a set superheat at the evaporator outlet, so its bulb must sense the suction line temperature there. It is clamped to a clean, straight, horizontal section and insulated so ambient air does not affect the reading.
Check it: RSOS task D-9 (installs metering devices)
Question 3 · D – Performs installation
Why should a horizontal suction line be pitched slightly toward the compressor?
Show answer without guessing
Answer: A. So oil carried by the refrigerant drains toward the compressor instead of pooling in the line
Oil leaves the compressor with the discharge gas and must return through the suction line. A slight pitch in the direction of flow helps gravity move oil to the compressor, especially at low loads when vapour velocity drops.
Check it: RSOS task D-9 (installs piping)
Question 4 · D – Performs installation
After brazing is complete on a new installation, which gas should be used to pressure-test the system for leaks?
Show answer without guessing
Answer: B. Dry nitrogen, regulated to a pressure no higher than the system's rated test pressure
Oxygen can react violently with compressor oil and cause an explosion, and compressed air adds moisture. Dry nitrogen is inert and dry. Always use a regulator and relief device and do not exceed the test pressure on the equipment nameplate.
Check it: RSOS task D-9 (installs HVAC/R systems – pressure testing)
Question 5 · D – Performs installation
You are wiring a single-phase compressor and measure these resistances: C to R = 2 Ω, C to S = 5 Ω, R to S = 7 Ω. Which terminal is S (start)?
Show answer without guessing
Answer: D. The terminal that reads 5 Ω to common and is part of the highest (7 Ω) reading
The highest reading (7 Ω) is across both windings, R to S, so the third terminal is common. From common, the lower resistance (2 Ω) is the run winding and the higher (5 Ω) is the start winding. Note 2 + 5 = 7, which confirms the windings are intact.
Check it: RSOS task D-10 (installs control systems – motors)
Question 6 · D – Performs installation
When installing a split air-conditioning system, why is a trap commonly installed in the evaporator condensate drain line on a draw-through coil?
Show answer without guessing
Answer: B. The cabinet is under negative pressure, so the trap seals the drain, stopping air being drawn in and holding water in the pan
With the fan pulling air through the coil, the drain pan sits under suction. Without a water seal, air rushes up the drain and condensate cannot leave, which can overflow the pan or blow water into the duct. A properly sized trap and slope prevent this.
Check it: RSOS task D-9 (installs HVAC/R systems – condensate)
Question 7 · D – Performs installation
A 40 VA, 24 V control transformer will supply relay and contactor coils that draw a total of 1.3 A. What is the transformer's rated secondary current, and is it adequate?
Show answer without guessing
Answer: B. About 1.7 A; adequate
Rated secondary current = VA ÷ volts = 40 ÷ 24 ≈ 1.7 A. The connected load of 1.3 A is within this rating. Coil inrush is several times the holding current, so leave margin.
Check it: RSOS task D-10 (installs control systems)
Question 8 · D – Performs installation
Which direction should the arrow on a liquid line solenoid valve point?
Show answer without guessing
Answer: D. In the direction of refrigerant flow
Solenoid valves rely on pressure difference to seat properly. Installed backwards, they may leak through or fail to close.
Check it: RSOS task D-9 (installs HVAC/R systems)
Question 9 · D – Performs installation
When installing a ductless multi-zone system, why must each line set be connected to the correctly labelled outdoor ports and matching wiring?
Show answer without guessing
Answer: D. Mismatched piping and wiring send refrigerant to one zone while controls serve another, causing faults
Each zone's piping and communication wiring must match. Cross-connection leads to one indoor unit icing while another gets no cooling. Many units have a wiring check function, but the installer must verify it.
Check it: RSOS task D-9 (installs HVAC/R systems)
Question 10 · D – Performs installation
When installing a potential relay for a single-phase compressor with a start capacitor, how is the relay coil connected?
Show answer without guessing
Answer: D. Between the start terminal and common, sensing the voltage generated across the start winding
As the motor reaches speed, back EMF across the start winding rises and pulls in the potential relay coil, opening its normally closed contacts and removing the start capacitor.
Check it: RSOS task D-10 (installs control systems)
Question 11 · D – Performs installation
When installing a crankcase heater on a compressor, how is it usually wired?
Show answer without guessing
Answer: A. Energized during the compressor's off cycle, often through a normally closed contact or as specified
Crankcase heaters keep oil warmer than the rest of the system so refrigerant does not migrate into it. They are typically energized when the compressor is off.
Check it: RSOS task D-10 (installs control systems)
Question 12 · D – Performs installation
What is the main purpose of a service valve on a condensing unit?
Show answer without guessing
Answer: A. To isolate the unit and provide gauge access for service
Service valves let technicians isolate parts of a system to hold the charge during repairs and attach gauges for readings and charging.
Check it: RSOS task D-9 (installs HVAC/R systems)
These are VoltExam questions written for the Red Seal Refrigeration and Air Conditioning Mechanic Interprovincial Exam, not official exam questions. Take the full free practice test or read the Red Seal Refrigeration Mechanic (313A) guide.
Last checked against Red Seal Program (with provincial and territorial apprenticeship authorities) on .
Practise Red Seal Refrigeration Mechanic (313A) by topic
Want every Red Seal Refrigeration Mechanic (313A) topic and the timed mock exams?
- ✓ 600 Red Seal Refrigeration Mechanic practice questions, every answer explained and cited
- ✓ Full-length timed mock exams: 125 questions, 4 hours, scored against 70%
- ✓ Practise by topic and review every question you missed
- ✓ Every other Canadian exam on VoltExam included
From
C$8.99/month
3-day free trial · or C$44.99 once for lifetime
Try all 600 free for 3 daysFree trial for new members on the Monthly plan, then C$8.99/month until you cancel. See all plans
Official sources
- Red Seal – Refrigeration and Air Conditioning Mechanic trade page ↗
- Red Seal – Refrigeration and Air Conditioning Mechanic exam information (breakdown) ↗
- Red Seal – Exam Preparation Guide ↗
- Skilled Trades Ontario – Refrigeration and Air Conditioning Systems Mechanic ↗
- Skilled Trades Ontario – Refrigeration and Air Conditioning Systems Mechanic (313A) 2025 trade report ↗
- Ontario – Certificate to handle refrigerants (ODP card) ↗
Sources checked November 14, 2026. VoltExam is independent and not affiliated with Red Seal Program (with provincial and territorial apprenticeship authorities). Rules change: confirm details with the official source before your exam.